SA24M014 – Construction of 500kV HVDC OHTL for COA- SOA (P-II)

Location
Wadi Al-Dawasir Site
Construction Date
2026-on going
CONTRACT VALUE(TON)
34620 MT
Status
Ongoing

The Purpose

Scope of Work: Execution of site logistics, field assembly, and structural erection for 500kV HVDC transmission towers, including:
 Logistics & Material Handling: Material sorting, bundling at store, and site transport.
 Assembly & Erection: Ground assembly, tower erection, and cleaning during assembly.
 Finishing & Quality Control: Structural tower tightening, Pal nut installation, torque
inspection, and final site restoration in compliance with SEC specifications.

Client

LARSEN & TOURBO SAUDI ARABIA LLC-(L&T)