


Location
Duba, Saudi Arabia
Construction Date
2023
Services
Ground Assembly, Tower Erection, Tower Tightening, Palmnut Installation
Project Type
High Voltage Power Transmission Infrastructure
The Purpose
ANC successfully completed the construction of a 380kV Overhead Transmission Line connecting Circle BSP to Dhuba Green. The project enhanced power transmission reliability through precise tower erection, structural assembly, and high-quality installation practices while meeting strict safety and engineering standards.

Client
Client: AL SHARIF GROUP & KEC (ASKEC)
Contract Value: 1,500 MT
Approx. Value: SAR 1.05 Million
Project Status: Completed
