Construction of 380 kV D/C OHTL Between HODN PV BSP -TEG BSP (Ck1&2)

Location
Turba
Construction Date
2024-2025
CONTRACT VALUE(TON)
5000MT
Services
3 Services Ground Assembly, Tower Erection, Tower Tightening and Pal Nut Installations

The Purpose

Execution of site logistics, field assembly, and structural erection for 500kV HVDC transmission towers, including:

  • Logistics & Material Handling: Material sorting, bundling at store, and site transport.
  • Assembly & Erection: Ground assembly, tower erection, and cleaning during assembly.
  • Finishing & Quality Control: Structural tower tightening, Pal nut installation, torque inspection, and final site restoration in compliance with SEC specifications.

Client

AL SHARIF GROUP & KEC-(ASKEC)